Monday, February 26, 2018
We have steel!
February 26th
The first steel beam is put into place at the West Regional Library.Photos by Doug LaFleur/LaFleur's Fine Photography.
Wednesday, February 21, 2018
We have a Foundation!
Finally a window of good weather to pour the foundation. The slab was poured February 15 for the West Regional Library. The job started at 4 a.m. and ended at 8:00 a.m.Photos by Doug LaFleur/LaFleur's Fine Photography.
We also had a great shot of the site provide by Developing Lafayette. https://developinglafayette.com/wp/new-public-library-under-construction-in-scott/
Thursday, January 04, 2018
Forming up a slab is boring from an onlooker's perspective. It looks like nothing is going on when there is a lot of activity but you can't see much from the road. That is where we are now with periods of wet and cold and the wait time as things dry out for work to continue. We hear the slab pour is coming later this month!
Monday, October 16, 2017
Friday, July 28, 2017
Tuesday, May 23, 2017
Thursday, May 18, 2017